Rehabilitation Of Dodo Pepesu – Nkwanta Road Project(46.4km) January 2015(progress Photographs)

REHABILITATION OF DODO PEPESU – NKWANTA ROAD PROJECT(46.4Km)

 JANUARY 2015(PROGRESS PHOTOGRAPHS)

F:\DCIM\101MSDCF\DSC03486.JPG

Final sub base preparation from Km8+775 – Km 9+825(LHS/RHS) prior to laying of crushed stone base course.

F:\DCIM\101MSDCF\DSC03485.JPG

Final sub base preparation from Km8+775 – Km 9+825LHS/RHS prior to laying of crushed stone base course.

G:\DCIM\Camera\IMG_20150112_110650.jpg

Backfilling to the barrel of the pedestrian Underpass at Km 14+565 in Brewaniase town.

G:\DCIM\Camera\IMG_20150113_121318.jpg

Laying of drainage pipes (PVC) for the pedestrian Underpass at Km 14+565 RHS in Brewaniase town.

G:\DCIM\Camera\IMG_20150113_114016.jpg

Construction of trapezoidal lined drain from Km 41+100 – Km 41+375 LHS.

F:\DCIM\101MSDCF\DSC03455.JPG

Construction of trapezoidal lined drain from Km 42+500 – Km 42+600 LHS.

F:\DCIM\101MSDCF\DSC03463.JPG

Construction of trapezoidal lined drain from Km 41+625 – Km 41+700 LHS.

F:\DCIM\101MSDCF\DSC03478.JPG

Slope protection at the outlet of the existing Box Culvert at Km 24+883 LHS in Salifukrom using    Gabion mattress.  

F:\DCIM\101MSDCF\DSC03466.JPG

Laying of Gabion mattress at the outlet of the existing Box Culvert at Km 24+883 LHS in Salifukrom.

F:\DCIM\101MSDCF\DSC03475.JPG

Laying of non-mountable kerbstones from Km 45+520 – Km 45+600 RHS in Nkwanta town.

I:\DCIM\Camera\IMG_20150118_080528.jpg

Construction of bicycle lane using paving blocks from

Km 44+300 – Km 44+400 RHS in Nkwanta town.

I:\DCIM\Camera\IMG_20150118_080423.jpg

Construction of bicycle lane using paving blocks from

Km 44+300 – Km 44+400 RHS in Nkwanta town.

F:\DCIM\101MSDCF\DSC03447.JPG

Erection of reinforcements for the walls of the Underpass at Km 45+120 in Nkwanta town.

G:\DCIM\Camera\IMG_20150127_170129.jpg

Concreting in walls of pedestrian Underpass at Km. 45+120 in Nkwanta town.

G:\DCIM\Camera\IMG_20150127_170124.jpg

Concreting in walls of the pedestrian Underpass at Km. 45+120 in Nkwanta town.

G:\DCIM\Camera\IMG_20150122_103900.jpg

Watering of crushed stone base course from Km 10+000 -Km 9+500 LHS prior to compaction.

G:\DCIM\Camera\IMG_20150122_163614.jpg

Compaction of crushed stone base course from Km 10+000 -Km 9+500 LHS prior to priming.

G:\DCIM\Camera\IMG_20150122_172221.jpg

Priming of crushed stone base course from Km 10+000 -Km 9+500 (LHS).

C:\Users\user\Desktop\PICS MARCH 2014\IMG_20140311_113957.jpg

Casting of concrete in base of the Underpass at Km. 45+120 in Nkwanta town.

C:\Users\user\Desktop\PICS MARCH 2014\IMG_20140312_114731.jpg

Casting of concrete for trapezoidal drain from Km. 42+500 – Km. 42+400 LHS in Nkwanta town.

C:\Users\user\Desktop\PICS MARCH 2014\IMG_20140312_114731.jpg

Laying of pavement blocks in cycle lane from Km.44+250 –  Km.44+350

RHS in Nkwanta town.

IMG_20141208_160408

Construction of cycle lane and walkway from Km. 44+375 – Km. 44+075 LHS in Nkwanta town.

C:\Users\user\Desktop\PICS MARCH 2014\IMG_20140312_114731.jpg

Backfilling to Box Culvert at Km.44+380 LHS.

IMG_20141212_154130

Construction of trapezoidal concrete lined drain at Km42+700LHS.

C:\Users\user\Desktop\PICS MARCH 2014\IMG_20140312_114731.jpg

 Concrete lining of embankment slope  at Km. 44+380 RHS.

G:\DCIM\Camera\IMG_20141210_113715.jpg

Installation of precast U-drains from Km. 44+050 – Km. 43+675 (LHS).

G:\DCIM\Camera\IMG_20141222_110208.jpg

Constructed trapezoidal lined drain from Km. 42+200 – Km. 42+325 (LHS).