REHABILITATION OF DODO PEPESU – NKWANTA ROAD PROJECT(46.4Km)
JANUARY 2015(PROGRESS PHOTOGRAPHS)
|
Final sub base preparation from Km8+775 – Km 9+825(LHS/RHS) prior to laying of crushed stone base course. |
|
Final sub base preparation from Km8+775 – Km 9+825LHS/RHS prior to laying of crushed stone base course. |
|
Backfilling to the barrel of the pedestrian Underpass at Km 14+565 in Brewaniase town. |
|
Laying of drainage pipes (PVC) for the pedestrian Underpass at Km 14+565 RHS in Brewaniase town.
|
|
Construction of trapezoidal lined drain from Km 41+100 – Km 41+375 LHS.
|
|
Construction of trapezoidal lined drain from Km 42+500 – Km 42+600 LHS. |
|
Construction of trapezoidal lined drain from Km 41+625 – Km 41+700 LHS. |
|
Slope protection at the outlet of the existing Box Culvert at Km 24+883 LHS in Salifukrom using Gabion mattress. |
|
Laying of Gabion mattress at the outlet of the existing Box Culvert at Km 24+883 LHS in Salifukrom. |
|
Laying of non-mountable kerbstones from Km 45+520 – Km 45+600 RHS in Nkwanta town. |
|
Construction of bicycle lane using paving blocks from Km 44+300 – Km 44+400 RHS in Nkwanta town. |
|
Construction of bicycle lane using paving blocks from Km 44+300 – Km 44+400 RHS in Nkwanta town. |
|
Erection of reinforcements for the walls of the Underpass at Km 45+120 in Nkwanta town.
|
|
Concreting in walls of pedestrian Underpass at Km. 45+120 in Nkwanta town.
|
|
Concreting in walls of the pedestrian Underpass at Km. 45+120 in Nkwanta town.
|
|
Watering of crushed stone base course from Km 10+000 -Km 9+500 LHS prior to compaction.
|
|
Compaction of crushed stone base course from Km 10+000 -Km 9+500 LHS prior to priming.
|
|
Priming of crushed stone base course from Km 10+000 -Km 9+500 (LHS).
|
|
Casting of concrete in base of the Underpass at Km. 45+120 in Nkwanta town. |
|
Casting of concrete for trapezoidal drain from Km. 42+500 – Km. 42+400 LHS in Nkwanta town. |
|
Laying of pavement blocks in cycle lane from Km.44+250 – Km.44+350 RHS in Nkwanta town.
|
|
Construction of cycle lane and walkway from Km. 44+375 – Km. 44+075 LHS in Nkwanta town.
|
|
Backfilling to Box Culvert at Km.44+380 LHS. |
|
Construction of trapezoidal concrete lined drain at Km42+700LHS.
|
|
Concrete lining of embankment slope at Km. 44+380 RHS. |
|
Installation of precast U-drains from Km. 44+050 – Km. 43+675 (LHS).
|
|
Constructed trapezoidal lined drain from Km. 42+200 – Km. 42+325 (LHS).
|